|
Ongoing construction of the Three
Gorges Dam is expected to ensure interception of the Yangtze
River between October and November next year. First phase of
the construction is being accomplished ahead of schedule.
The project officially started in December
1993. By the end of 1995, 108.8 million cubic metres of
earth had been removed and 1.35 million cubic metres of
cement placed.
The only delay experienced was
in the building of a highway linking the dam site with the
nearest city, Yichang, where the Three Gorges company is
based.
The road, originally scheduled to open
to traffic in June, will not be ready for another one to
three months thereafter.
But a bridge spanning
one of the three gorges will be built in March, three months
ahead of schedule.
The pressure to start the
second phase of construction in early 1998 did not force the
company to exceed its budget.
Invested capital
by the end of last year totaled 11.5 billion yuan, with
20-30 percent of the total used as working capital, 0.8
billion yuan spent on heavy-duty equipment and almost 7.5
billion yuan on infrastructure.
At present,
construction of a 350-meter-wide diversion channel is in
full swing on the right bank of the Yangtze and a temporary
shiplock 60-90 metres high is also under construction.
During the second phase, the dam will be built
to a height of 87 metres and by 2003, the first turbine will
have been installed on the southern bank to start generating
power.
When the second phase is completed, 14
turbines and a 135-metre-high permanent ship-lock will have
been built on the southern bank.
In the final
phase, the dam will be raised to a maximum height of 175
metres and an additional 12 turbines will be installed on
the northern bank of the Yangtze River.
|
|
|